In which tables can i find ECM header statuses (approve, close, check ECR...etc) and Object managment records statuses (change possible, release change etc)
I checked many tables like AENR, AEOI, and few others but no use. Please help me here
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Maruti
Are you using Engineering Change Request(ECR) ?
You can get the status of Change master in table AENR, field name AENST.
For OMR, in table AEOI refer the field name CCSTO.
Can you be more details about the scenario you are working on .
Cheers
Satish