Change a price control from V to S for a valuates Sale / Project stock

Former Member
0 Kudos

HI Experts Is it possible to change a price control from V to S for a valuates Sale / Project stock (not in the material itself by mm02) Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

kamalkumar_biswas2
Active Contributor
0 Kudos

Hi

   Price control change from V to S is possible but in following cases you can't do that:

     1. If the material is subject to split valuation

     2, If standard cost is coming from costing and not equal to MAP (V)

   Other than above 2 conditions you can change