on 12-16-2014 8:48 AM
Good Morning
I recently uploaded a solution of 6.0 EHP1 manager at SAP SOLUTION MANAGER 7.1 and after the climb version is failing the job LANDSCAPE FETCH, and I get the following message "The SLD server connection is inactive", have made the following test Call transaction SLDCHECK to check the connection to the SLD and SLDAPICUST to verify that it works the sld and I replied that is correct.
Best regards
Marcos A. Monzón
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check job log in sm37. You will get root cause for job failure.
Regards,
Deeraj Shetty
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The message that gets me the job log is as follows and I've done all the tests I listed in my previous comment.
Job 9:46:04 started
9:46:04 Step 001 started (program RSGET_SMSY, variant & 0000000000012, user ID XXXXXXX)
9:46:05 The SLD server connection is inactive
9:46:05 Job canceled after system exception ERROR_MESSAGE
Best regads.