on 12-16-2014 6:53 PM
Hello ,
I have plan for 12 month.Demand entered in MD61
Dec 100 Jan 300 and so on..
Out of which for first 4 months system generate PR
and after that planned orders needs to generate after MRP.
Is this possible?
Thanks,
Harish
Hi Caetano
procurement type is E only.
please refer the attached file in earlier post.
I will explain once again
Material A is fert .
Demand entered for A for 12 months
Need is that A should be
having PR for 4 months and later planned order After MRP.
but in actual only Raw material PR generated for 4months and later planned order.
Thanks
Harish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Harish
Did you check if you have the creation indicators on the MRP group, as described on the document below?
Indicator 'Create Purchase Requisitions' is not considered by MRP
BR
Caetano
Hi Harish,
As I understood your requirement is to create Pur Req within Opening period and Planned Orders outside the opening period. To achieve this you need to first change the configuration setting for Creation Indicator as said above by Caetano in OPPR ( Change Create Purchase Req = 2)
Then maintain opening period in Schedule Margin key and assign this key in MRP2 view.
Please note that the Procurement Type should be External procurement "F". In this case the BOM will not be exploded while MRP run because of external procurement.
Also please take care that you should have the requirements in system outside the opening period which you defined in Schedule Margin Key.
Hope this helps.
Thanks
Nitin
Hi Harish,
Also I have found that with procurement type "X" and special procurement type "20", you can achieve the desire results.
You need to check the checkbox of "Also plan unchanged components" while MRP run for this material. (Ssytem will explode the BOM while MRP run)
System will generate the PurReq in opening period if indicator "2" (Create Purchase req) is selected on the MRP screen. (Irrespective of what is maintained in creation indicator config - OPPR).
Thanks
Nitin
Hello Nitin and Caetano,
Thanks for the reply.
I have one question related to this Total horizon plays any role with this?
If I understood correctly only child material those are with procurement type F only generates PR in opening period and later Planned order.
Header Material with Procurement type E are not working in this way it always creates Planned order.
Since I tried with all setting suggested by you guyes , but only ROH material (Child part) generates PR in opening period and later planned order get generated for that child part.
But still header FERT material is having Planned orders only.
Is this behaviour is correct?
Thanks,
Harish
Hi Harish,
Try following settings in your Header material master.
Set procurement type = X
Special Proc key = 20
Now if your demand is greater then your opening period defined in Schedule margin key, system will generate Pur req within opening Period and Planned order outside the opening period.
Components assigned under Header materials will behave according to the material master settings and planned with MRP run if "Also plan unchanged components" check box is selected during MRP run.
Regards
Nitin
Hello
Yes, this is possible. You should create a scheduling margin key where the opening period is 4 months (transaction OMDC). After that, assign your scheduling margin key to the material master and make sure that you are running MRP with the parameter
Create purchase req. = '2 - Purchase requisitions in opening period'
You may also define this value as default on the creation indicator of the material master. See this document for details:
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.