on 12-18-2014 4:23 AM
Dear all,
I need to calculate breakdown duration in SAP by excluding break timings based on shifts. Is it possible to configure in standard through maintenanc ework center? Please clarify.
Thanks in advance.
Regards,
Nellaiappan N.P.
Hello Nellaiappan,
A very natural and basic doubt every member would get here about your query is why you are relating the Technical Object to the MainWorkCenter. What is this situation asking for such report ? However, in case I chose to answer this, then it would be as under:
It is assumed that your query is about the Malfunction Notification field AUSZT. If you want to deduct the WorkCenter break duration from this value (from AUSZT value), then go for a development.
But as I said, it is difficult to understand the reason for the requirement of such report.
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please use the below function module and try to use with your scenario,
CX_SCHED_VIA_OPERATING_TIME
This FM will calculate breakdown duration based on the capacity calculations in workcenter.
Regards,
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Regards
Varun.M
Hi,
Thanks for your valuable & helpful reply. I have tested in my development client. Please find the below screenshots & I have given the inputs as mentioned in your previous reply and got the outputs. But the duration calculated is 1406 sec, but for the given inputs it should be 1500 sec. So Please clarify on what logic, duration is calculated in the FM.
Request your inputs please
Please find the screenshots also,
FM Input
FM Output
Dear All,
Thanks for your valuable replies and i will calculate the same using User exit with the help of ABAPER's and herby I have closed the thread also.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nellaiappan,
As per your query in standard SAP it is not possible to calculate breakdown hours shift wise.
You can develop customize field shift in order / notification for tracking shift wise report .
IW41 this transaction use for calculating actual labour working hour on that breakdown.
So I hopeful this will help you.
Thanks,
Sagar Kumbhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your reply. But my client dont want to use IW41 separately but the system should calculate the breakdown duration by excluding break timings automatically. Is it possible through shift definitions & shfit sequences & breakdown schedule by mapping it with maintenance work center?
Hi Nellaiappan,
As far as i have seen, there is not standard option available to get this calculation.
Since the Break down duration is calculated from the time equipment is breakdown and once the equipment is back to operation. So this will calculate the total history.
You need to develop a custom functionality to get your issue resolved.
Regards
Terence
User | Count |
---|---|
89 | |
7 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.