Component Material Change in Process Order

Former Member
0 Kudos

Dear Members,

As i create a process order through COR1, the component material 0010 is going changed in process order Material List.

All the screen shots are as below:

BOM :

RECEIPY:

PROCESS ORDER :

You can see the material component 0010 is changed from 101020001 TO 107020018.

also note that material description remain same as BOM

Required your help as earliest as possible.

Thanks & Regards,

Dharmendra C. Gohel

Accepted Solutions (0)

Answers (2)

Answers (2)

kiran_kumar179
Active Contributor
0 Kudos

Dharmendra,

You have already posted same question this week

What is the use of posting same question in same week?

Your issue could be because either of below reasons

1.Someone might have changed the item in order

2.There could be Alternate item defined for same component either in material master or BOM item details.

You need to ensure all these checks are in place and still if you found same issue I suggest you to debug the order creation for BOM explosion and see from where that item is being picked.

BR
KK

former_member201849
Contributor
0 Kudos

Hi Dharmendra

Please check Production Version (C223) because there might be link with alternative BOM and Master Recipe.

Regards

SURESH.M

Former Member
0 Kudos

Hi,

Also Check any Alternative BOM is selecting, any version is defined.

Also Check In master recipe any material quantity calculation and any formula written to change the material based on the header material quantity.

Br,

Ravi

Former Member
0 Kudos

Dear Suresh,

I had checked the production version. it found ok.

Thanks & Regards,

Dharmendra C. Gohel

former_member184737
Active Contributor
0 Kudos

Dharmendra,

     Could you please share the screenshot of component 102020001's basic data view in BOM? What is the plant specific status value for the component?

Thanks

Former Member
0 Kudos

Dear Sankar,

Please find screen shot for the material.

Thanks & Regards,

Dharmendra C. Gohel

sjeevan
Active Contributor
0 Kudos

Hi,

Check if you're using engineering change management.