on 12-18-2014 8:10 AM
Dear Members,
As i create a process order through COR1, the component material 0010 is going changed in process order Material List.
All the screen shots are as below:
BOM :
RECEIPY:
PROCESS ORDER :
You can see the material component 0010 is changed from 101020001 TO 107020018.
also note that material description remain same as BOM
Required your help as earliest as possible.
Thanks & Regards,
Dharmendra C. Gohel
Dharmendra,
You have already posted same question this week
What is the use of posting same question in same week?
Your issue could be because either of below reasons
1.Someone might have changed the item in order
2.There could be Alternate item defined for same component either in material master or BOM item details.
You need to ensure all these checks are in place and still if you found same issue I suggest you to debug the order creation for BOM explosion and see from where that item is being picked.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Dharmendra
Please check Production Version (C223) because there might be link with alternative BOM and Master Recipe.
Regards
SURESH.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.