on 12-20-2014 10:29 AM
Dear All,
When we try post MIRO using delivery note it is automatically adopted wrong payment term which is not in Vendor master as well as not in Purchase order, except of this if I try to post using PO it is adopting correct payment term but user want to post MIRO using Delivery note only, kindly let me know from where the wrong payment terms is adopting. Moreover I checked vendor master centrally XK03 but didn't find anything wrong.
Hi Revankumar,
check this OSS Note:
SAP Note 322430 - MIRO: Proposal logic for terms of payment
https://service.sap.com/sap/support/notes/322430
It will definitely help you..
Or check whether BADI "MRM_PAYMENT_TERMS" is active in your system..?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Both,
Thank you for your reply, I found the answer in SAP Note 393431 but got reference of this note from SAP note 322430. If MIRO is posting with reference of Delivery note then MIRO will adopt the payment terms from the very first of delivery note once you adopt it in MIRO, since delivery note has many PO's along with our concern PO.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In standard, system will only take the PO payment term in MIRO and by the way, system will not take different payment term with regards to reference of PO and delivery note.
I assume there are some custom development is running in your system. Have a look into the blog if you have little knowledge about custom development or you can show this to your ABAP team to check further.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.