Progress Controlling with PS

Former Member
0 Kudos

Hello colleagues,

In the moment we are searching for possibilities to measure the progress of our projects in SAP. We are working with detail WBS Structure and networks.

Because of this we plan to use the costs and hours to to generate a progress grade automatically.

Is this possible in the Projectsystem?

Thanks

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Thank you very much. We will try this.

BG Johannes

Former Member
0 Kudos

Use CNE1/E2/E5 transactions.

Also read the below threads:

Progress Tracking - SAP Library

Regards

Shishir

MTerence
Active Contributor
0 Kudos

Hi Johannes,

You can achieve it by Progress Analysis

Progress Analysis - Project System - SAP Library

As mentioned by Paulo, Measurement Method is a part of Project Analysis

But in case if you want very simple way of project analysis, you can use CNS41 transaction.

Regards

Terence

Paulo_Vitoriano
Active Contributor
0 Kudos

Hello Johannes,

Please refer to below link for possible Progress Measurement Methods:

Define Measurement Methods - Project System - SAP Library

What you did mentioned looks similar to Cost Proportionality and Quantity Proportionality.  Besides you can simply use Estimate, that is when the business user does personal estimation in % value.  Sometime that can be most accurate, since not dependent on neither plan nor actual data.

Automatic is nice, but requires good quality of plan data, as well as proper accruals for actual data.  Your actual cost in the system is normally either behind or ahead of real work progress.

Regards,

Paulo