How to do read PP master data for process order with system status CRCR?
Requirement from my client is after control recipe is generated, process order status is CRCR.
But due to some wrong entry user want to do some changes in process order as process order is already released,
user want to set process order status CRTD, but after CRCRC status is active READ PP MASTER DATA option
is gets disable.
Any suggestion how to bring back READ PP MASTER DATA option?
Hello Vishal,
This is as per the standard SAP design.
If the master data is now read for this order, the status 'Released' and the status 'Control recipe created' iscancelled. After re-release, it it is now possible to create a second productive control recipe for the same control recipe destination.
The status 'Control recipe created' is forbid the rereading of the master data.
Transaction BS22 system status
Double-click on the entry for system status I0241 (CRCR - Control recipe created). This brings you to the maintenance of the business transactions which are coupled to this status. the business transaction RMNS (Reread master data) to 'Forbidd.'. I will not suggest you to change it to Allowed.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.