on 01-24-2015 7:41 AM
Dear Experts,
I am encountering a typical error whenever trying to execute PT60 on public holidays with time entry in IT2011. My public holidays configuration is proper is reflecting properly in work schedule as shown below.
However whenever we are running PT60 say on 25.12.2014, following dump is triggering.
Please, someone help me urgently to resolve the issue
Regards
Tandrima
Hi Tadrima,
Have you written any custom PCR in the schema? It's saying the arithmetric calculation is giving such a answer which is overflowing.
Generally this error occurs when you have inserted any custom pcr and there you have wrongly maintained operation or any wrong calculation.
Regards,
Sankarsan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sankarsan
Thanks for your inputs
Yes, i do have custom PCRs after P2011 function as shown below. But those PCRs are working fine for any other working days scenario, only public holiday cases, its giving the dump not sure why and also see below the line of function P2011, where it is getting terminated.
Please help
Hi,
Deactivate line no:- 000230 & 000240 and then check that error is coming or not.
Change the PCR like below for your requirement
ZOVH
*
****
VARSTHOLCL
*
COLOP *
1
VARSTPRSNT
N
COLOP *
Y
HRS=PEND
HRS-PBEG
ADDDBZOVHZ
ADDZL 9OVH
COLOP *
Usr this pcr with function PTIP with Par2 as GEN . Insert this PCR just after P2011 function and then check again.
Regards,
Sankarsan
ABAP Runtime error SAPFP5IT Please debug...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.