Hi All,
i am using Standard Quota functionality. I am doing third party/subcontracting process with two different BOM's. So I am using quota on production version basis with procurement type "F" and Special proc. Type "L" in MEQ1.
As per standard behaviour and quota system is splitting my requirement against two production versions. But for 2nd purchase requisition which MRP is generating its not picking the BOM components.
I have tried the same with In house manufacturing case also with Procurement type "X" but still the 2nd planned order generated with 2nd production version is not picking the BOM.
Please help ASAP on this issue.
regards,
Vikash Kumar
Hello
I wrote the following document about the most frequent issues related to BOM explosion that may be useful to you:
For this specific problem, make sure that the following notes refered on the document are implemented on your system:
1791009 - No BOM explosion after changing production version
1781324 - MD11: Valid BOM alternative is not found
Regards
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
It's a program error. You should implement the mentioned notes to solve this issue.
Even if the symptom described on the note does not fit exactly into the issue observed on your system, I have seen similar issues in the past and I can tell you that these notes will probably solve the issue.
Regards
Caetano
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.