        I try running maintenance plan costing for multiple counter plan from IP30 but this error appear "no maintenance plan costing"  any ideas

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Mohamed,

Well, do you have any more info on the 6 points mentioned in the application help? Also, is your Factory Calendar valid for the scheduling period?

Former Member
0 Kudos

i have checked all the points and when i am running this transaction IP30 for strategy plan or single cycle the error does n't appear 

Former Member
0 Kudos

the feature of determining cost or multiple counter plan is available ??

sebastian_lenartowicz
Active Contributor
0 Kudos

Greetings Mohamed,

Apparently not:  "You cannot perform a costing for multiple counter plans."

See: Maintenance Plan Costing - Customer Service (CS) - SAP Library

MTerence
Active Contributor
0 Kudos

Hi Mohamed,

Refer below link

Maintenance Plan Costing - Customer Service (CS) - SAP Library

You cannot perform maintenance cost for multiple counter plan