on 01-26-2015 2:58 PM
Hello,
I currently have many projects open in SAP CO that I do not want to remain open as people still have the ability to post time and costs to these projects. They are all currently in PREL status (partially released) however I would like to close them in SAP.
When I use the CJ20N transaction to close these projects, I get the an error message stating "Balance of WBS is not zero". What does this mean and how can I eliminate it?
Please can someone help?
Many thanks,
Nikesh
Thanks everyone for all your help. I have passed this on to our SAP BA team.
Many thanks for your replies.
Nikesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
I tried to run the CJ88 for a particular WBS as per the suggestion above however it comes back with an message that I need to "Maintain the settlement rule of the sender". Any ideas how I do this?
Many thanks,
Nikesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Paulo.
If I run a CJI3 query that gives me the history of all the postings to date since it's inception. Do these balances need to be brought down to "zero"?
Sorry for all the questions!
Many thanks.
Nikesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nikesh,
It means that in the settlement profile customizing you have a mandatory settlement option for WBS-elements.
Whether that is right or wrong depends on your specific business scenario.
To set a Closed status for WBS you need to run a settlement to bring balance down to zero (or change the customizing). Anyway that is just one of the pre-requisites for closing, but there are others too (like no outstanding commitments for example).
Regards,
Paulo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nikesh,
There are open PO exist for the WBS element or Network Activities or WBS is not settled completely.
You need to run settlement for the WBS element, then try to close the WBS element.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Nikesh,
You need to use transaction CJ88 and execute the WBS element.
Run in test mode to confirm the cost and then execute without test run.
If this is possible....You can execute CJI3 for each project with includes settlements in the report, so you will know what are the WBS element are not fully settled.
Else you will come to know when you try to close the WBS element.
Regards
Terence
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.