Does any one know of any; config, BADI or enhancement that will let you influence the length of the demand header in the planning board. As a I asked in a previous post:
1. Is it possible to use the scheduled start and finish dates.
2. Is there a user exit / BADI.
Why would you want to do this? Good question :
1. I am using the Basic Dates for another reason (reporting purposes) and they are set not to be updated.
2. I am not scheduling all of the operations in MRS and I would like the demand header to 'span' the length of the operations that are included in the planning board.
Thanks
Stewart
Hi Guys,
The scheduled start and end dates of the header are integrated out of box .
You may refer to the MRSS DB table /MRSS/D_DEM_H.
Cheers!
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Stewart
There is a BAdI, but I am not sure whether that may help you or not but might be worth to take a look at it:
- BAdI: Integration of Maintenance/Service Order with MRS (ERP)
There is a method PUSH_TO_MRS in thaty BAdI, which might be the one you are looking for.
Good luck and please let us know whether that helps or not.
Regards
Savas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.