on 01-26-2015 9:15 PM
Hello all.
On some facilities we have a work order type where system status PRC will be used (CRTD MANC PRC). But a different facility but the same work order type will not have the PRC.
Why? Is this something added or checked during the creation of the plant? Or is this something I missed in PM configuration?
Hello
Please consult with your FICO Person.Might be preliminary cost estimate does not exists for an order ( product cost collector or manufacturing order).
Br
Rakesh