on 01-30-2015 12:11 PM
Dear PM Expert,
When we time confirm the Maintenance Order using T-code IW41, Is it possible to automatically determine Actual duration by subtracting Work Finish from Work Start?
(Eg: the same way which Breakdown dur. Calculates based on Malf.start & Malf.End )
Can the system propose Actual duration based on Work Finish/Start times
Please advice.
Thanks
Ashok M
Hello Ashok,
You need to explore one of the following user-exits
CONFPM01 PM/SM order conf.: Determine cust. specific default values
CONFPM02 PM/SM order confirmation: Customer specific input checks 1
CONFPM03 PM/SM order conf.: Cust. spec. check after op. selection
CONFPM04 PM/SM order conf.: Customer specific input check 2
CONFPM05 PM/SM order conf.: Cust. specific enhancements when saving
As the names indicate the first and the last exits in the above list should help you.
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.