status maintenance order ILNC

Former Member
0 Kudos

dear all

if status maintenance order ILNC (inspection lot not created) after released.

1. check configuration order type vs inspection type (14)

     SPRO path : IMG > Plant Maintenance and Customer Service > Maintenance and Service Processing >Maintenance and Service Orders > Functions and Settings for Order Types > Assign Inspection Types to Maintenance/Service Order Types


2. check inspection point 300 (inspection point for equipment) in QM data - Task List Header

3. check task list already assigned to maintenance plan and status task list is released

4. check sampling procedure - inspection points already ticked "Plant Maintenance"


last , if you think all setup is OK, check:

5. if you was upgraded for basis release 6.20, see the sap note : 572103 - No inspection lot for maintenance order


(cek this link)

https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/sno/ui_entry/entry.htm?param=69765F6D6F6465...

Symptom

No inspection lot is generated for the maintenance order. Status I0182 ILNC 'Inspection lot not

created' is assigned to the order.

In the release log, the system generates message CO548 'Material &1: automatic generation of

inspection lot failed'

Reason and Prerequisites

The units of measurement Customizing was changed for Basis Release 6.20. Instead of the old ISO code

PCE, new ISO code C62 is now used for 'piece(s)'.

As a result, there is no longer any unit of measurement in the standard Customizing which has ISO

code PCE. During inspection lot creation, it is therefore not possible to determine any unit of

measurement for the inspection lot.

Solution

Maintain an unit of measurement with ISO code PCE:

Customizing -> General Settings -> Check units of measurement tcode CUNI

Pushbutton 'Units of measurement', selection '(no dimensions)'

Choose an appropriate unit of measurement such as ST or PC or create a new unit of measurement.

Maintain ISO code PCE on the detail screen.

6. After you configure ISO code, check and test. The maintenance order will generate inspection lot after released.

7. If you have maintenance order with status REL ILNC before, don't worry, you still can generate inspection lot but manually.

Go to the Change Maintenance order, then select Order in toolbars , select function --> inspection lot --> create inspection lot. Then the maintenance order will generate inspection lot.

Accepted Solutions (0)

Answers (1)

Answers (1)

busyaban7
Active Contributor
0 Kudos

Hi Sri,

We also had same issue in past. Please create a new custom unit of measure ZPC and assign ISO code PCE to it. Once you do it, in QE51N screen the units for inspection will be ZPC (instead of PC) which is exactly same as PC and you will be able to create an inspection lot for PM order. There is no other known work around available to my understanding.

Note that, before creating this new UoM ZPC, please can you do downstream impact analysis on IDOCs transferred to any other SAP systems, etc and speak to business stakeholders on this issue after fixing it.

Thanks,

Arijit

Message was edited by: Arijit Banerjee