on 02-25-2015 5:15 AM
Hi All,
Scenario:Step 1) Pre bid estimation team to make the cost plan ie Version 0
Step 2 ) proposal team to evaluate teh cost plan and save it as Version 1
step 3) Procurement estimate team to check / make changes if any and save as version 2.
Is it any way possible that I can maintain 3 versions of the cost plan. if yes kindly guide me how to go about .
How can I transfer the cost maintained in (cj40) to original budget (cj30 ).
Thanks
Suvin.Sugathen.
Hi Suvin,
You can create different Cost Plan version using t-Code OKEV. maintain the Plan cost Versions 1 & 2 by copying the version 0.
Once you are done with creating Cost Plan versions your end users can create different cost plan versions in CJ40.
Coming to Copying the CJ40 values to CJ30:
In standard CJ40 plan version 0 cost is displayed in Planned total Column in CJ30. you can copy this cost into the original budget.
if you want to copy the final cost plan which is plan version 2 into Budget.. Then you need to transfer the Plan version 2 cost into Plan version 0 using CJ9FS..
Hope it helps..
Regards
Samar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Refer SAP Help, Search forum.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Suvins,
create version profile in OPTS if you want to create project version automatically on basis of status.
if you use manual project version then use CN72.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.