Hi Experts,
We are facing an issue while copying data to Direct Update DSO(Planning Enabled).
We are trying to copy data from real time infocube into planning dso (aggregation level based on composite provide which is union of realtime infocube and planning dso).
If all the keyfigures values are 0 in the infocube, then those records are not copied to the planning dso.
Whereas if the key figures has values, then those records are copied.
We have used the standard copy function.
When exceuting the planning sequence for copy function, the empty records are read but the combinations are not copied.(Ex: 11100 records read, 0 generated, 0 changed).
Also checked the settings of the standard planning function. Process Empty Records checkbox is enabled.
Yet when Keyfigures are 0, those records are not copied.
Is this the Planning DSO limiation?
Any pointers will be of great help.
Thanks in advance.
Regards,
Priyanka
Hi Priyanka,
please open a ticket and we will look into it. Fhe findings in you case we then can put in this blog again. Please just tell us the ticket.
Regards
frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Priyanka,
this is the standard behaviour for standard planning functions and also for fox.
A zero will not be written to the cube or DSO.
regards
Cornelia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
there is one standard function which is able to write zero-record.
it´s the creation of records according to characteristic relationships.
this one would create a zero record for each possible combination.
depending on the numer of records you could run this one before your copy.
but I am not sure that this function works on a DSO, I never tred that.
regards
Cornelia
Hi Cornelia,
Thanks for your reply.
We have tested out the copying between two realtime infocubes, and it copies even the 0 records.
In SAP BW 7.4, there are two copy functions.
1. Copy ( 0RSPL_COPY)
2. Copy ( without records where all keyfigures are zero ) (Techincal: 0RSPL_COPY_NO_ZEROS)
The copy function( 0RSPL_COPY) is designed to copy even 0 records. Hence the process empty records checkbox enabled and the copy function with no zeros(0RSPL_COPY_NO_ZEROS) does not have the process empty records checkbox enabled as it should not copy the 0 records.
But the same functionality is not working on Planning enabled DSO.
Any pointers on this.
Regards,
Priyanka
User | Count |
---|---|
85 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.