on 02-26-2015 12:20 PM
Hello,
I have maintained the below MRS setting in config node
Define Resource Planning Relevance for PM/CS Orders (ERP)
I have maintained 2 lines
1)) operation control key , plant, order type, a order user status called STOP with planning relevace
2) Operation control key plant, order type, order user status STRT with planning relevavce ticked.
But when I create orders, I am not able to see the order with STRT status on planning board which it should as per config.
Can anyone gude on this , if any config is missing?
Hi ,
Is the PMcS- MRS integration BAdI acive?
Do you see the orders being integrated to MRS DB table /MRSS/D_DEM_H ?
Cheers!
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.