Hi Gurus
My client is using PP-PI and have only one resource.
In prod. versions always two operations are maintained paralelly eg.: 0010 and 0020 (use the same resource)
0020 phase contains the fix and variable proc time.
When a plan order is generated of course two operations exists
My client during detailed production planning doesn't want to see in CM21 the two phases for one order. How can I remove operation 0010 or 0020 from screen in CM21? Shall I modify the sorting?
Thanks for your help
Hello
If you don't want to see one of the operations on capacity leveling, make sure that you are using a control key that does not generate capacity requirements.
In addition, since you are working with process orders you should use the standard overall profile, "SAPPI_G001" on CM25 or transaction CM29.
Regards
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.