- My problem is : I have a sales order and one item's material is 'A' .
- I run MD50 after that the planned order is created for 'A' material.
- After MD50 running , i've changed the item's material with 'B' and i run MD50 again.
Now i have two plannned order with 'A' and 'B' material number. But i want to delete planned order 'A' material number.
How can i solve this issue ? When i run MD01 the problem is solved. But i don't want to run MD01 because i just want to run mrp after sales order creation.
Best Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
This is as per the standard SAP system design. So in such cases if you run MD01 /MD02 will delete all these order.
Or run transaction MDBT or program RMMRP000 to remove such orders.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.