on 02-28-2015 11:07 PM
Hi,
Despite the daily MRP job runs with NEUPL parameter, it doesn't select all the materials and we have some materials that hasn't been planned for one day.
¿Any idea of what could be happen?
Thanks.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Oscar,
As stated above please show us the MRP views for that particular materials?
Also show MD04 snap shot and Please check any Planning file entries exists for those materials for NEUPL in MD21 as Regenerative planning (NEUPL): System plans all the materials that are contained in the planning file.
If not create a planning file entries MD20 or in background in MDAB and re run MRP.
BR
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Óscar,
Note that NEUPL runs the MRP only if the material has an entry in the any planning file entry (MD21).
NEUPL does not create any planning file entry. Check this note:
206666
- MRP: Control parameters during planning
With MDAB you can generate entries in the planning file entry in background.
Kind Regards,
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There could be multiple reasons for the same. The materials you are referring are never planned before? If so, please check the MRP type in material master. If that is not PD or VB, then (say something like ND) it will not be planned.
another reason could be your selection in MRP run.
Please specify more details
Thanks
Prem
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.