Dear Gurus
I am not able to the change the investment cost in plan value tab after creating an appropriation request. We have done an upgrade from ECC6 to EHP6. Earlier we were able to change. We want to change the plan value ,since an approximate value is entered while creating and later, on we change the value to the cost incurred.
Please help
Regards
Vidhyadharan
Hello Vidhya,
Also check below SAP note
1884400 - Unable to change the ECP cost estimate
201517 - Updating plan values for appropriation requests
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vidhyadharan,
Kindly raise a OSS note to SAP.
I guess below note will be the solution, but check with SAP.
1999315 - IMA11/12/13: Appropriation requests can no longer be displayed or changed
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.