on 03-04-2015 9:23 AM
Dears,
I have a doubt with my MTO cycle, i proceed with the below cycle:
1- Create sales order (100 PC , Rev 1000, cost 800)
2- Mark the sales order cost
3- MD02 to create planned orders
4- MD04 transfer the planned orders to PR and Production order
5- after the purchasing cycle and GR the raw material
6- issue the raw material on the production order
7- Gr the finished product
8- make the delivery and billing (the billing didn't get transport to CO-PA which is right)
regarding the CO
1- Settle the production order (the production variance transferred to CO-PA)
2- Result analysis run (the revenue is 200 !!!)
3- during settlement the sales order (it post 200 to CO-PA)
I was expecting that CO-PA will be effected by 1000 REV value field and 800 Cost COGS value field.
i'm missing something or this is the standard behavior!.
Thanks and Regards,
Ahmed Samir
Hi Ahmed,
I experience the same in our last project
While settling to COPA it is getting net off (Revenue-COGS) profit part is getting transferred to COPA
This is standard behavior
We didn't get time to explore further
Thanks and regards
VSN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Actual scenario flow like below where sales order is not a cost object.
regarding the CO
1- Settle the production order (the production variance transferred to CO-PA) -> it is correct and WIP can be calculate if production order not delivered to sales order.
2- Result analysis run (the revenue is 200 !!!) - > not required.
3- during settlement the sales order (it post 200 to CO-PA)-->> not required.
During the billing, COPA document should be created. for this, you need to define item category in sales view YMTO which will derive YM in sales order and you can calculate WIP based on production orders.
Regards
Shalin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dears,
Any thoughts if COPA should read el net between the cost and revenue ,, or it's the right thing to happened!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kamal,
Thanks for your respond however, i'm using a sales order costing.
but during settlement of production order the variance transferred directly to COPA
what i'm talking about is the settlement of sales order and result analysis "KKA3, VA88"
is the above the standard behavior or not.
Thanks and Regards,
Ahmed Samir
Dear Kamal,
The config for the Req. class is as below:
Account assignment categorty : E
Valuation : M
settlement profile : SD1
Result analysis key : SDOR1
costing : X (costing required)
Costing id : B (Automatic costing and marking)
costing variant: PPC4
Condition for line item :EK01
so what can i change in order to send to copa the revenue and the cost not the net between them.
Regards,
Ahmed Samir
User | Count |
---|---|
101 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.