03-10-2015 10:09 AM
Hi,
Is it possible to generate Gantt charts in SAP commercial project management.
Please advice.
Shubham
09-16-2015 10:52 AM
Hello Shubham,
As of CPM 2.0 you can display a Gantt Chart of the linked PS Project, this gantt chart is created with a java applet. It looks quite nice, see the screenshot.
regards, Johannes
09-16-2015 10:52 AM
Hello Shubham,
As of CPM 2.0 you can display a Gantt Chart of the linked PS Project, this gantt chart is created with a java applet. It looks quite nice, see the screenshot.
regards, Johannes
10-08-2015 12:00 PM
02-26-2016 7:41 AM
Hello Johannes,
Can you please guide me on how to generate this with a java applet.
Any reference documents available with you?
Thanks
Shubham
02-26-2016 2:16 PM
Hi Shubham,
i remember no specific configuration Settings. As soon as you have linked a PS-Project to your masterproject and you are in the Workspace, you mark the PS-Project Header and then select "Display gantt Chart" from the Dropdown above the structure Display. then the Applet should be loaded.
it may well be that you must activate specific PS Business functions. Check if you have Transaction PSHLP10 available. if not, activate the Business functions for PS: OPS_PS_*
regards,
Johannes
02-27-2016 2:20 AM
Hi Johannes,
I activated necessary Business Functions for executing PSHLP10/20 as highlighted below :
However ,the Gantt Charts are not getting displayed.
Can you suggest some way to resolve this?
Thanks
Regards
Shubham