Hi,

     In the tcode RECN ( we rent some land ). We want a distribution on profit center on condition. One or more condition we want to distribute two profit center, example 40% on one PC and 60% on a different PC. I look at the distribution formulas but I did not found my solution.....

SAP ECC 6.0 HP 5

Best regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

bowen_cao
Contributor
0 Kudos

Hi,

Please check below KBA for your question:

1789489 - Assignment of more than one profit center to a real estate contract is not possible

Thanks and regards,