HI
I have user requirement to create this report:
Controlling Area Currency CAC | Object Currency (OC) | Amount to be returned calculation | Amount to be used for Budget Return | ||||||
Budget (CAC) | Actual (CAC) | Remaining Budget (CAC) | Budget (OC) | Actual (OC) | Remaining Budget (OC) | CAC Remaining Budget converted to OC using Budget rate (OC) | OC Remaining Budget converted to CAC using Budget rate (CAC) | ||
(1) | (2) | (3) | (4) | (5) | (6) | (7) = (3) * Budget rate | (8) = (6) / Budget rate | if (8) => (3) then (7), else (6) | |
Project 1 | |||||||||
Project 2 | |||||||||
Project 3 | |||||||||
Project 4 | |||||||||
Project 5 |
My dilemma is wich tool to use to build the report & how.
CJE2 & CJE6 Project Hierarchy Reports
I have managed to create columns 1 - 6 using a copy of forms from SP1 Reporting Group
but I fail to create "IF - then" formula
GRR2 Report Painter
SP1 & SP2 Reports are not available there to copy from, while SP3 has no Budget data available
GR32 Report Writer
I'm just not sure how to manage it & where to start from? Is that realistinc to do without special training?
Please could you help me to figure out how can get to deliver that user requirement?
What shall better do?
Thank you very much in advance,
Daria
Hi Daria,
Better use your technical guys help and develop a Custom report.. I don't think you can achieve it by modifying the standard reports using Report Painter..
You can use RPSCO, COSP, COEP for plan and actual cost values and BPJA/ BPGE for budget related data..
hope it helps..
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Daria,
In addition to what Sunil has mentioned , i think you don't need to get into the AFVC table unless you are using network activities under the WBS. Even then I don't see a need for AFVC as your budgeting is at the WBS level.
And your requirement is to capture Budget, Actual Cost and Remaining Budget and Return as per your formula.. here You should be looking at the below tables:
1. PROJ : For Getting the list of Project.
2. PRPS : for getting the WBS for the Projects..
3. COEP or COSP OR RPSCO.
Though you can get all your values in RPSCO but this is a huge table and you can hit some performance issues.. So you can use COEP or COSP ( if you want to use Line items or totals)..
Rest you can go with the logic given by Sunil.. Just filter the values by the Value type for each project and you should get your desired result..
Regards
Sammar
Hi Daria,
you should go for table COEP. in this table you will get all currency postings (Object Currency as well as Controlling are currency).
if you want logic than let us know.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
please check below logic:
Select * from PROJ
Pass project to PRPS-PSPHI and fetch PRPS-POSID, PRPS-ONJNR
Pass Selected WBS to AFVC-PROJN and fetch AFVC-OBJNR
Pass PRPS-ONJNR & AFVC-OBJNR to COEP-OBJNR and fetch COEP-BELNR, COEP-WTGBTR where COEP-WRTTP=4 and VRGNG NE KOAO
also get below fields from COEP as per requirement:
WTGBTR-Value TranCurr
WOGBTR-Value/Obj. Crcy
WKGBTR-Val/COArea Crcy
thanks
Sunil