I need to configure ABAP based PI sheet for goods issue for Process order.
Issue with PI sheet after configuration.
1. In PI sheet header material for process order is also occurring for consumed quantity.
2. Do i need to set up filter with control recipe destination?
3. is it required to maintain Process instructions at both places master recipe and control recipe destination.
Regards
Manish Gupta
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do check attachment. For detailed steps
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Manish,
Characteristic PPPI_RESERVATION_ITEM in the process instruction and generate the process instruction automatically. Then, the characteristic PPPI_RESERVATION_ITEM must not be valuated in the master recipe. Instead, it is automatically valuated during the generation.
Check in O12C enter Plant and Go to CONS_D- Click on Characteristics and look for PPPI_RESERVATION_ITEM. Here you will find that there is a column V (Value Assigned to Characterisitc)
Also use O10C to generate the required process instruction.
Please refer this discussion on same issue.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
10 | |
5 | |
5 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.