production order settlement process.

Former Member
0 Kudos

Hi PP guys,

My client requirement to full settlement production orders, accordingly  I configured in OPL8 "order type dependent parameter" PP2 default rule in controlling tab, now for some material (semi finished) when I create order it is taking PP1 (fully) and for some material PP2 (periodic) settlement. all required setting ok, but I doubt about "over head group" differ material to material in material master. some body tell why it is taking for some material  PP1 and for some material PP2. I guess there is some setting in material master and controlling but not found perfect.

Please provide correct solution with thanks in advance.

its urgent.

regards,

Amit Awasthi.

Accepted Solutions (1)

Accepted Solutions (1)

former_member184627
Active Contributor
0 Kudos

Dear Amit,

The settlement profile is picked up based on the settings maintained in the order type dependent parameters (OPL8).

Selection of order type is based on one of the below methods:

1.In material master, work scheduling view the prod scheduling profile is assigned. Based on the prod scheduling profile the order type is picked (OPKP).

2. Based on the prod scheduling profile assigned to the production scheduler (OPJ9)

3. Based on plant parameters (OPPQ)

4. Based on the MRP group OPPR)

PP2 (periodic settlement) is normally maintained for joint production Eg: Co-products. Do you have co-product scenario for some materials ?

For full settlement use PP1.

Regards,

Senthilkumar SD

Former Member
0 Kudos

Hi senthil,

  thanks for reply, actually client don't have co-product material, but BOM  level by level maintained.

I configured PP1 fully in OPL8 not PP2 (by mistake wrote PP2), but still I am able to settlement order fully in K088, is this sufficient in term of order settlement ? there is no any production order profile / scheduler maintained in material master "work scheduling " screen also.

regards,

Amit Awasthi.

former_member184627
Active Contributor
0 Kudos

Dear Amit,

In KO88, when you execute with Test run, due you get any error message ?

Is the production order Technically completed (TECO) ?

Regards,

Senthilkumar SD

Former Member
0 Kudos

Hi Senthil,

  When I execute KO88 then two message display.....

in green signal: sender ORD XXXXXX (material description).

in yellow signal: profitability segment being derived again.

I enter, then settlement screen display.

regards,

Amit.

Former Member
0 Kudos

yes order has been techo then do settlement.

former_member184627
Active Contributor
0 Kudos

Hi Amit,

Once the order is set with TECO, we go for settlement. Once settlement is compelted, we close the production order. I understand that you have completed the settlement now.

Or do you still have some issue. Also, confirm with your FICO consultant.

Regards,

Senthilkumar SD

Answers (0)