Planned & confirmed labor hours for Work Center

sarabindu_roy
Explorer
0 Kudos

I searched through SCN & different forums for solution, didn't get much.

Our business needs a report that shows following:

  1. Planned labour hours per Work Center via Routing for a date range.
  2. Confirmed labour hours per Work Center for a date range.

Standard tables point to operation-wise values while requirement is for individual Work Centers labor hours.

Any help on how to get these values will be appreciated. Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Try with transactio COOIS.

BR
Caetano

sarabindu_roy
Explorer
0 Kudos

Don't see labor hours on COOIS with all list options. Moreover data stored in structures. Can you help further please.