Configurable Tasklist - PM

Former Member
0 Kudos


Hi everybody,

I have a question concerning the use of configurable tasklist.

Is it possible to insert a configurable tasklist via IW32 to an order which have already a task list(non configurable).

thanks for your answers.

Nathali.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

Hi Nathali,

Are you getting a "Characteristic Value Assignment Screen" after selecting the Task list group and counter in the Work Order? If yes, then you have to specify the characteristic values of order equipment over there.

Regards,

Summan

jogeswararao_kavala
Active Contributor
0 Kudos

I think so, you can do it from the Order menu Extras > Tasklist selection > Direct Entry.


Related link:



KJogeswaraRao

Former Member
0 Kudos

Hello , Thank you for your answer. I have tried but it doesn't work. The system add my new configurable tasklist (3 operations) but not completely ( the operation with the dependance (the third) is not added). And i don't know the reason. I suppose that it's because there is already a tasklist in the order or some operations but normaly I think , it shoudn't be a problem.