In the current situation all the labour hours, energy units are input manually at the month end in respective process orders so as to book the costs. Since the process order volume is huge,this slows down the month end closing process. Also the labour and energy data are available on a weekly basis.

Is there a way (Configuration/Workaround) to automate the booking of these costs either at the month end or during the week end so as to not wait until month end.

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Use COHVPI - Mass processing confirmation (select function 200 - Confirmation)

or CORR - Collective entry


Also you can use Bapi BAPI_PROCORDCONF_CREATE_ACT - Enter Activity Confirmations for Process Orders


Please refer SAP help link,

Mass Processing of Process and Production Orders - Production Orders (PP-SFC) - SAP Library

Best Regards,

R.Brahmankar

Answers (1)

Answers (1)

jason_shao
Employee
Employee
0 Kudos

Dear saravanan,

I found your question is more about the confirmation process in Product planning scenario. I think the place here maybe more suitable to ask this question:

http://scn.sap.com/community/erp/manufacturing-pp/content

Best regards,

Jason

Former Member
0 Kudos

Sorry Jason