schedule a job with dependancy in Redwood.

Former Member
0 Kudos

There are 5 jobs like A, B, C, D, E. job B, C, D depends upon success of Job A. But job E depends upon Only job D. Here my question is how i schedule job E, which only depends upon D. Step 1 A, step 2- B,C,D and step 3 -E.  here step 3 depends upon all 3 jobs to complete, which i don't want. i want job E depend only Job D. is there any option in redwood to for such dependance.

Accepted Solutions (0)

Answers (1)

Answers (1)

h_carpenter
Active Contributor
0 Kudos

Hi puranjaya swain,


The easy solution:


Put D and E in a separate chain, call that chain from this one.


Regards,


HP