Hi All,
We have maintained the settlement rule as "FUL" for the Order Type. This can be achieved for Independent Orders, but while doing doing for the Collective Order with Work in Process type system is taking "PARTIAL".
Can any one explain the reason for it.
Hello,
In Customizing for the order type it is set that orders should be settled periodically (default rule PP2). However, this is not supported for subordinate orders in the collective order.
For this collective order, the system sets the default rule to PP1 regardless of the settings predefined in the order type. Then the collective order is subject to full settlement.
200060 - Periodic settlement in the collective order
Please check if you have any custom development for settlement.
If not then raise this to OSS.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.