Hi
We use Check-time with an Argument of 10Min at pre_Batch_start at an Operation. Now, if time was longer, the start is prohibited, as required.
Now I wonder, what the recommended Setup for SAP ME Looks like:
- is there any way to allow the start by qualified personel, e.g. reset the Limit
- or do we Need to have an Operation in parallel in case, the time was overdone
- or is there an other function?
Kind regards
Yvonne
Hi Yvonne!
- is there any way to allow the start by qualified personel, e.g. reset the Limit
No. I don't know if it works but you can try to re-route the SFC to a different operation and then come back.
- or do we Need to have an Operation in parallel in case, the time was overdone
It could be a solution.
Or you can assign the hook to one resource but having another resource without this hook for the same operation. You can consider using Certifications to limit an access to this operation/resource.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.