SUM - Upgrade Near-Zero Downtime RUN_CRR_LAST Error

former_member229542
Active Participant
0 Kudos

Hi guys

While running an ERP EHP7 Upgrade, in phase RUN_CRR_LAST Phase im unable to proceed.

First this phase failed since PXA was too small, so many tables cancelled, therefore I fixed this issue by increasing abap buffersize parameter and no more dumps were found

So, when I try to restart the SUM Process Im stuck in this phase

In the logs its states

1 ETQ359 RFC Login to: System="TEX", AsHost="ARBUE-V-SA03D" Nr="02", GwHost="ARBUE-V-SA03D", GwService="sapgw02"

2 ETQ232 RFC Login succeeded

4 ETQ010 Date & Time: 20150417150518 

1 ETQ233 Calling function module "SUBST_CHECK_BATCHJOB" by RFC

2 ETQ373 parameter "JOBNAME" = "RSUPG_ISU_CRR"

2 ETQ373 parameter "JOBCOUNT" = "15051800"

2 ETQ373 parameter "IV_VERIFY" = " "

1 ETQ234 Call of function module "SUBST_CHECK_BATCHJOB" by RFC succeeded

4 ETQ010 Date & Time: 20150417150518 

2 ETQ373 parameter "JOBSTATUS" = "F"

2 ETQ374 parameter "RC_CHECK" = "0"

2 ETQ373 parameter "JOBENDDATE" = "20150417"

2 ETQ373 parameter "JOBENDTIME" = "150518"

4 ETQ263 Batchjob "RSUPG_ISU_CRR" finished successfully

1 ETQ124 Scanned file 'log\RSCRRLST.TEX' from offset 17273 to 18454 for errors.

4 ETQ010 Date & Time: 20150417150519 

1EETQ399 Last error code set is: Single errors (code <= 😎 found in logfile 'RSCRRLST.ELG'

1EETQ203 Upgrade phase "RUN_CRR_LAST" aborted with errors ("20150417150519")

Batchjob "RSUPG_ISU_CRR" finishes successfully, but some how it says it found an error in log RSCRRLST.ELG


RSCRRLST.ELG

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Final data transfer of change recording framework ERRORS and RETURN CODE in RSCRRLST.TEX

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

A4 ESUPG 002 " "

A4 ESUPG 001 -------------------------------------------------------------------------

A4 ESCRR_ISU 005 Action "LAST" started at "15:05:18"("17.04.2015")

A4 ESCRR_ISU 010 Number of used dialog processes set to "6"

A4 ESCRR_ISU 010 Number of used dialog processes set to "10"

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed


And that log only says


Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed



Im able to login to shadow instannce - Transaction CRR_CONTROL and its in yellow state, ready to be started.



If I started in manually, the upgrade says there is another so It has to be stopped. Then i restart the SUM process and it fails again



RSCRRLST.ELG

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Final data transfer of change recording framework ERRORS and RETURN CODE in RSCRRLST.TEX

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

A4 ESUPG 002 " "

A4 ESUPG 001 -------------------------------------------------------------------------

A4 ESCRR_ISU 005 Action "LAST" started at "15:05:18"("17.04.2015")

A4 ESCRR_ISU 010 Number of used dialog processes set to "6"

A4 ESCRR_ISU 010 Number of used dialog processes set to "10"

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed



RSCRRLST.TEX

A4 ESUPG 002 " "

A4 ESUPG 301 Report name ...: "CL_CRR_BASE_SCENARIO -> CONSTRUCTOR"

A4 ESUPG 302 Log name .: "E:\SUM\abap\tmp\RSCRRLST.TEX"

A4 ESUPG 304 Start time.....: "17.04.2015" "15:05:18"

A4 ESUPG 002 " "

A4 ESUPG 001 -------------------------------------------------------------------------

A4 ESCRR_ISU 005 Action "LAST" started at "15:05:18"("17.04.2015")

A4 ESCRR_ISU 010 Number of used dialog processes set to "6"

A4 ESCRR_ISU 010 Number of used dialog processes set to "10"

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed

A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed

A4 ESUPG 001 -------------------------------------------------------------------------

A4 ESUPG 002 " "

A4 ESUPG 301 Report name ...: "CL_CRR_BASE_SCENARIO -> CONSTRUCTOR"

A4 ESUPG 304 Start time.....: "17.04.2015" "15:05:18"

A4 ESUPG 305 End time ......: "17.04.2015" "15:05:18"

A4 ESUPG 002 " "

A4 ESUPG 001 -------------------------------------------------------------------------

4 EPU202XEND OF SECTION BEING ANALYZED END OF RUN_CRR_LAST =================================================

Any idea how to fix this?

Best

Martin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Same Problem Heree

anandkarthik_raja
Active Participant
0 Kudos

Hi Jorge,

Could you please let us know the status of the phase RUN_CRR_LAST .

Regards,
Anand.

Former Member
0 Kudos

Hi Anand,

I have open a Support ticket.

       Checks after phase MAIN_SWITCH/SUBMOD_SWITCH_OLDREL/SUBMOD_CRR_LAST_CHTRANS/RUN_CRR_LAST were negative!

Last error code set: Single errors (code &lt;= 😎 found in logfile 'RSCRRLST.ELG'    

       Batchjob RSUPG_ISU_CRR on shadow system failed.
Detected the following errors:

# K:\usr\sap\TD4\EHP7\SUM\abap\log\RSCRRLST.xx:
A4 ESUPG 302 Log name .: "K:\usr\sap\xx\EHP7\SUM\abap\tmp\RSCRRLST.xx"
A4 ESUPG 304 Start time.....: "23.04.2015" "09:34:54"
A4 ESUPG 002 " "
A4 ESUPG 001 -------------------------------------------------------------------------
A4 ESCRR_ISU 005 Action "LAST" started at "09:34:54"("23.04.2015")
A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed
A2EESCRR 097 Transition "LAST_TRANSFER" can not be started because transition "START_TRANSFER" failed


I already restarted the  Server, ABAP, DB and SUM.

I checked the table CRRERROR and it hast 200 entries one of them has for example the table T5SKT

when I check the table CRRTASKINFO on the field ADDCHAR1 with T5SKT. It has no error status. I think that the Error is there but I that SAP confirms this to me.

Regards

Jorge



anandkarthik_raja
Active Participant
0 Kudos

Hi Jorge,

-Have you already checked the SAP Note:1678564 .

-Also you can try the following

-stop the transfer in CRR_CONTROL,

-restart the shadow instance

-start the transfer in CRR_CONTROL

-if it is green, stop the transfer

-repeat the phase

Regards,
Anand.

Former Member
0 Kudos

Hello All,


We solved the problem ! The trick was step 4 ! Repeat the phase without init !


Dear Customer,

Could you please perform the following,

1. stop the transfer in CRR_CONTROL in shadow instance

2. restart the shadow instance

3. start the transfer in CRR_CONTROL in shadow instance

4. if it is green, stop the transfer

5. repeat the phase in SUM

This should solve the issue. Please let me know the outcome.


Upgrade to EHP7 742 release

anandkarthik_raja
Active Participant
0 Kudos

Hi Jorge,

Glad to know that the issue has been solved.Please close the thread and please provide your valuable points or ratins.

Regards,
Anand,

Former Member
0 Kudos

Hi Anand,

I´m not the owner of the thread..

Answers (4)

Answers (4)

former_member229542
Active Participant
0 Kudos

Thanks guys for providing assistance

anandkarthik_raja
Active Participant
0 Kudos

Hi Martin Simois,

Glad to know that the issue has been solved.Please close the thread.


Regards,

Anand.


Former Member
0 Kudos

@Martin Simois check my post.

Regards

Sriram2009
Active Contributor
0 Kudos

Hi Martin

Could you check this SAP Note 1678564

BR

SS

former_member229542
Active Participant
0 Kudos

Hi SS

I have already check this note on a previous error regarding PXA buffer size, unfortunately there is no description of the issue Im facing at the moment

Best

Martin

Sriram2009
Active Contributor
0 Kudos

Hi Martin

Refer this SAP KBA 1979466


BR

SS

former_member229542
Active Participant
0 Kudos

Hi SS

That note was also helpful before entering Downtime, and a couple of tables were in Black Status and after restating I was able to move on

Sadly, this is no applicable to the situation Im experiencing now,

This same situation happened or another system being upgraded.

I proceeded to Start / Stop CRR Process and then I was able to restart SUM and continued to the next phase, but it does not seems to work on this system being upgraded

Its running an a SQL Server 2012 so it should not be a problem

former_member229542
Active Participant
0 Kudos

In CRR_CONTROL, Im able to start process manually and there are six CRR process running in Background

My concern, should I wait until this job completes? Its been running for over 75.000 seconds and writing the CRR Logs in SUM Folder

If i Stop it, and the try to continue with SUM, it displays the message stated above

and if I dont stop it, SUM stated there is a duplicated Replication Process Running

Any idea how to troubleshoot this?

Best

Martin

former_member229542
Active Participant
0 Kudos

I let the Replication process ran for almost a day, it never stopped. Then I proceeded again to stop from CRR_CONTROL.

Restarted SUM Phase, and somehow it managed to continue, it stated it could not finish scanning file CSCRRLST_5, retry again and completed this phase.