Dear colleagues,

I found an issue during V_V2 rescheduling where GR time in material master seems not to be considered.

Please see the following example:

  • After creating an STO and running ATP on it manually, I receive the following schedule lines result.

  • Executing V_V2 for this material only and STO documents I see how the GR end date has changed and no longer considers the GR time of 4 days.

Does somebody know if there is a note that solves this situation already?

Thansk for your time in advance!

Salvador

Accepted Solutions (0)

Answers (1)

Answers (1)

Prasoon
Active Contributor
0 Kudos

Hi,

   Please check the note:  1758558 - GR end date is cleared with backorder processing  which addresses a similar issue. Hope the same can solve the above issue.

Regards,

AKPT

Former Member
0 Kudos

Dear Prasson Ak,

Thanks for your answer, Unfortunately I had already checked this note without success.

The reason being that the modification that it proposes is only relevant in the following form:

FORM PURDOC_PREPARE_MEKET

This form is entered based on the following condition


IF t_eket_new[] IS INITIAL.


in my scenario, t_eket_new is always filled in so this form is always skipped.


Any other ideas?


Thanks again!

Salvador

Prasoon
Active Contributor
0 Kudos

Hi,

   In that case, I would suggest to raise an OSS ticket to SAP!!

Regards,

AKPT

Former Member
0 Kudos

Dear AKPT,

I have done like you propose. Let´s see what SAP proposes. I will keep you posted.

Thanks