on 04-20-2015 7:24 PM
Hi ,
Please let me know,if we can schedule a bunch of tasks in information steward in a single go .
I understand that we can schedule multiple tasks at the same time separately .
But I have around 750 tasks which are to be scheduled at the same time .
Regards,
Althaf
Hi Altaf,
Select all the objects (Profile/Rule task inputs) which you want to execute, name the clubbed task and Save. Then you can schedule this master task. Hope it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply Devilal Rajappan , I am looking at the "Schedule"/"Recurrence" option in CMC .
I tried selecting multiple tasks and schedule them as a single clubbed task,but CMC doesn't allow me to do so
Please let me know how we can do it either through Information steward or through CMC
a. Select views (In case of rule tasks).
b. Click "Calculate Score"
c. All the selected views will be listed, provide max input sixe, sampling rate etc. Provide "Clubbed task name" and click Save.
d. Login to CMC.
e. Information Steward --> Data Insight --> Projects --> "Project Name" --> "Clubbed task name".
f. Right click and schedule.. This will execute all tasks selected.
Appreciate your quick responses devi,
"Information Steward --> Data Insight --> Projects --> "Project Name" --> "Clubbed task"
I can't select multiple tasks in CMC the Control Key on Key board doesn't help
Do we have an option for creating some thing called Clubbed task?? Am in missing some thing ?? Please help