on 04-21-2015 8:23 AM
Dear folks,
I have following requirements:
Customer orders Material A and for some reason (e.g. low stocks), the mrp controller decides to produce an alternative material (B) which is
equal to Material A. This also counts for planned independent requirements.
How can I maintain this in SAP? I tried to use alternative item group in the BOM, but this does not solve my requirement, since this is just a function to assign an alternative BOM position for Material A. I really need to assign an alternative material on header level.
The assignment has to take place before actual production. We cannot use Material Determination (SD) - Transaction VB11.
Any ideas? Is this something we have to develop?
Kind regards,
Peter
Hi Peter,
your requirement is not totally clear to me.
When material B is produced instead will you change the material in the sales order manually?
Is this about consumption of planned indepednent requirements?
Please help me to understand.
Cheers,
Uli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Peter,
Check these links for discontinuation parts:
Discontinued Parts - Material Requirements Planning (PP-MRP) - SAP Library
Regards,
Anupam Sharma