on 04-29-2015 11:41 AM
Hallo!
We'd need to include the work description of employee time recordings in time sheets (e. g. available in Report employee times: montly) in project reports (e.g. Project line items).
Does anybody have an idea?
BR, Roswitha
Hi Roswitha,
you could create a new Data Source (Join Type: Left Outer Join) based on DS Project Line Items (as Anchor DS) and Project Expense Item. Join Criteria would be Project and Project Task and you join the Work Description to the Project Line Items:
Then you have to create a new report based on this DS.
Best regards
Henriette