Configurable process scheduling(CPS) for STO

Former Member
0 Kudos

Hi All,

We are implementing CPS for STOs but its not getting triggered with schema SCHEDL_SDD and SCHEDL however its working for sales orders.

We have done all the configuration based on this document -

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/902a053e-398c-2d10-ab8b-8e71ca42c...

Is there any additional settings/configuration required or we need to use any specific schema to make it work for STOs ?

Your help will be highly appreciated

Thanks,

Vinay

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vinay,

I'm currently facing the same issue for STO. Did you find a way to solve this problem?

Kind regards,

JP

thiagoalbieri
Member
0 Kudos

It is necessary to configure CPS and assign schema with an empty item category. I had same issue some years ago.