Hi Experts,

There is a requirement to integrate the multiple ERP backend systems to the single UWL XML in SAP Enterprise Portal 7.3 .

Any suggestions will be welcome!

Best Regards,

Tarun Dhuria

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Experts,

I am able to integrate the Multiple backend systems with multiple clients to the UWL by making changes in UWL XML file. keeping all the system alias with the task Id in the XML.

Thanking you for expert suggestions, it really helped alot!

Best Regards,

Tarun Dhuria

Answers (1)

Answers (1)

kiruthika_s
Active Participant
0 Kudos


Hi Tarun,

By default when you create a webflow connector for different backend system and register an xml file will get created.Your scenario is possible its purely on the high priority xml file configuration.

Check the below help link to know on uwl configuration DTD:

Configuration DTD - Configuring the Universal Worklist - SAP Library

The itemtype in the xml file defines the task behavior,read the item type help link how it will be considered

Item Type - Configuring the Universal Worklist - SAP Library

uwl.task.webflow.***Taskid****.system

so you can stop in the definition at the level of uwl.task.webflow in the high priority xml file,then for the tasked it will search and take the xml file which holds it.

Regards

Kiruthika

Former Member
0 Kudos

Hi Kiruthika,

Thanks for the reply,

I am configuring Universal Worklist from Portal... It work's fine when i use it only for one ECC system i.e only one System Alias for a ECC system.... But I want to use UWL for Two different ECC system .... for a same EP user...

In short .... UWL for Two different ECC systems..... For single EP user.


Waiting for the response!


Best Regards,

Tarun Dhuria

kiruthika_s
Active Participant
0 Kudos

Hi tarun,

you can use N number of ECC system in uwl

If you take portal User A the same User A should exist in all your Backend system ECC X,ECC Y,ECC Z

For each ECC system the system object need to be created in portal with different system alias and a connector need to be created in UWL admin configuration.

Regards

Kiruthika

Former Member
0 Kudos

Hi Kiruthika,

Thanks for the Response!

Will try the suggested solution and update you!

Thanking You!

Best Regards,

Tarun Dhuria

Former Member
0 Kudos

Hi Kiruthika,

I have tried, when i click on the workflow of System A, its working fine, but when i click on the workflow of system B, it stays at Portal, It doesn't connecting to the Backend system.

Moreover, we are using Custom XML file for the UWL.

Any suggestions will be welcome!

Thanking you in advance!

Best Regards,

Tarun Dhuria

junwu
Active Contributor
0 Kudos

what is "Stays at portal, didn't connect to backend?"

Former Member
0 Kudos

Hi Jun Wu,

Thanks for the response!

Worklist stay at Portal, it not able to go back to the backend, but for the Other worklist which is connected to other system is able to back the backend system.

Thanks in the Advance!

Best Regards,

Tarun Dhuria

junwu
Active Contributor
0 Kudos

you mean opening a task?

kiruthika_s
Active Participant
0 Kudos

Hi Tarun,

Is all the backend webflow connector status are succesfull in uwl iview-manage connection status?

Are you getting any error when you launch the workitem in uwl?

Regards

Kiruthika