Task list does not Exist error-In Production version details

0 Kudos

Hi,


Find below image,Kindly let me know what i supposed to correct in this production version

Accepted Solutions (1)

Accepted Solutions (1)

former_member185450
Active Contributor
0 Kudos

Dear Sankaraditya,

Please ensure the valid from date of the Rate routing (CA22) the date should be lies with in the PV valid period

same way please maintain the log size 1 to 99999

then check the PV system will pick the valid rate routing details

Regards,

Venkatesh..

0 Kudos

Hello Venkatesh

can you plese let me tell this

1.how do we configure group in planning data(2nd image).

2.in image one i can't find frpm lot size & to lot sizethat screen in ca22

and canu plz send me step to step process of rem and its integrations

Regards

Sankaraditya

UmeshMali4994
Active Contributor
0 Kudos

Hello Nadella,

Please refer the below document for REM step by step process

go through above document and understand the REM process and replicated in your system.

For Prod version in REM, go to MRP4 view and maintained Prod version 

1. BOM, go to CS01

2. Routing/Rate Routing CA01/CA21

Group is nothing but your Routing/Rate Routing number which created when you first time create Routing/Rate routing in system. With same group number you created one more time Routing/Rate Routing with different counter number.

Maintained same Routing/Rate Routing mention in production version and Check.  

Go through the my document which is very useful to understand the REM full cycle..

If you have any issue let me know..

Thanks & Regards

Umesh Mali

rajesh_madham
Participant
0 Kudos

Use c233 to mass process the prodution versions

Answers (3)

Answers (3)

former_member185450
Active Contributor
0 Kudos

Dear Sankaraditya,

After saving the Routing / Rate routing system will generate Group / Group counter number.Through this Group / Group counter you can able to find the Routing / Rate routing details in the data base (Table)

once you open the CA21 / CA01 in header only you can able to find the from lot size to To lot size

suggest you to read the basic threads from SDN for knowledge instead of posting this kind of issues..



Regards,

Venkatesh..

UmeshMali4994
Active Contributor
0 Kudos

Hello Sankar,

Production version has combination of the BOM and Routing

In REM, you can create the Routing or Rate routing, Make sure you maintained the valid date. .


In REM,  you can enter routing or Rate routing in prod version. (Routing has some limitation in REM)


CA21 : For Rate routing

CA01 : For Routing


When you enter Task list in production version, make sure you enter the valid Group and Group counter number


Please check and revert

Thanks & Regards

Umesh Mali

dejoy
Active Contributor
0 Kudos

Where is the image? Check whether the task list or group or group counter is correct.

Regards