Hi,
We are using sequencing dependent planning in PPDS by using setup matrix & other relevant master data.
We have a requirement that when user creates a planned order manually system should notify to the user that setup matrix is not used.
1 Will system considers setup matrix during manual creation of planned order?
2 If not what is the suggested mechanism of notifying the user.
regards,
Mohit
Hi Mohit,
If order is getting created with scheduled status it will refer to set up matrix even during manual order creation. If you are creating orders with deallocated status using ppds enhancement then it will not use set up matrix.
Regards,
Santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mohit,
If there is no predecessor order before order created then it refers to setup matrix value where predecessor is *or initial and sucessor is set up group of current order. Hence it is reocmmende to have some value of set up duration for with combination of 8 as predecessor.
Regards,
Santosh