Hello Gurus

We are Implementing Top_down Budgeting solution Via SAP CRM using BW-BPS & PS. We needed some help in integration.

When Budget is planned at Marketing plan & hierarchy  level it goes in BW system & a Project/WBS is created in PS.

Now point here is that budget should be committed through BW & available in ECC (PS). This is where we are not clear as to how this work.

we referred to a couple to links & blog like

Marketing Planning and Budgeting (SAP Library - SAP Brand Management)

Please help us understand the link between BW & ECC for Budget transfer

Regards

Rohit

Accepted Solutions (0)

Answers (1)

Answers (1)

surjeetbhati
Active Participant
0 Kudos

Hi Rohit,

In CRM system, Go to transaction SPRO and follow the path: SAP Reference IMG>Strategic Enterprise Management-->Define Target Systems.

Here, the logical systems should be maintained. In RFC Destination column, give the logical name of the BW system. Then you can find the planning profile which was created in BW system in CRM system.

And then follow the steps given in the below document:

http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/b0641069-9f1c-2e10-70ae-d131e7af9f10

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/509ae952-91af-2e10-d8b3-9fd5d34e4...

Hope this resolves your issue.

Regards,

Surjeet Bhati

Former Member
0 Kudos

Hi Surjeet

Thxs!!

My context is regarding BW & ECC (PS) integration for Marketing Budget (Top-Down budgeting).

Once Marketing Plan is created budget flow to BW & in BW after approval or commitment it is available in ECC (PS). This is where I need some help.

Regards

Rohit

surjeetbhati
Active Participant
0 Kudos

Hi Rohit,

The planned cost for various activities is entered in CRM using planning profile in the marketing planner and then the actual cost is entered manually in the WBS structure and corresponding purchase order is raised in ECC-PS module.

WBS element created in ECC gets updated and stored in BW, Once you have your project/WBS elements/structures in BW, you can use the BPC's standard functionality of loading master data using BW Info Object and get that information into your BPC System and later extract the analysis reports

It's bit tricky you need to check more from BW side

Regards,

Surjeet Bhati

Former Member
0 Kudos

HI Rohit,

What exactly is your requirement? Can you put it in question form?

Rgds

Hari

Former Member
0 Kudos

Hi,

Need experts thoughts.

We are using Top down Budgeting in Our Marketing Plan & in the process, when we click on 'Budgeting' tab after creating marketing Plan etc & the next screen is not coming up which is explained in the below link from help.sap.com.

Using Top-Down Budgeting - Marketing Resource Management - SAP Library

.

In the screenshot provided above, the first 3 steps detailed in the procedure are working but not the 4th step for which the next page should appear after clicking the 'Budgeting' tab in which the complete hierarchy of marketing projects that belong to the marketing plan is seen.

As this 4th step is some thing to do with the BW Integration, we are not sure what is missing.

We did all the necessary settings as mentioned in the below link that details the steps related to 'Make System for Topdown Budgeting'.

https://www.consolut.com/en/s/sap-ides-access/d/s/doc/YY-CRM_MKTPL_RFC_TDB

Regards

Kumar