Hi,


Scenario: Two Different projects Common & Phase in SAP Project System. Phase is successor of Common. Cost of Common should be transfer to Phase and Settled to WIP (Work-In Progress). Last Financial year Common WBS is settled to the WIP G/L Account, and Closed. Now, the cost of same WBS should be transfer to Phase WBS.

We made Credit Entry to Common WBS and Debit entry to Phase WBS with Constant G/L Account and Amount in current year. While CJ88 process of Common WBS it shows me Message no. KD213 ( WBS is already settle or there nothing to settle ). While CJI3 shows Credit entry against Common WBS.

Kindly Help me with this issue

Regards

Omkar Deshpande

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor

Hi Omkar,

Please check if your settlement rule type is FULL or PER (Periodic).  Since PER will look only for specific period (current period by default).

Also can be a good idea to check your posting dates selection criteria in CJI3, so maybe it is a zero balance in the accumulated view.

Regards,

Paulo

Former Member
0 Kudos

Hi Paulo,

Thanks for your reply.....

My Posting Date is 1st April 2015, and settlement rule type is PER for April-May 2015.

Regards,

Omkar