SES budget exceeds error , SES unable to release as budget exceeds by 9,558 in WBS .
In WBS only one WO is created which is for simplex and against that WO two line items are using this WBS . The amount which is assigned as per WO line items is not matching with the BVA & CJI5 report .
Assigned As per BVA Assigned As per WO Diff
44,448,975.46 = 44,582,333.00 - 133,357.54
Committed As per BVA Committed As per WO Diff
113,193.72 = 123633.726 - 10,440.01
Help Me to solve.
Hi,
Can you post the screenshot from report S_ALR_87013558
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Omkar,
I dont see any problem here. How you calculate the BVA ? or what report you check for BVA ?
Bit of analysis require on this ? As this is only one order, you need to check the actuals / commitments per line items. Also is there any PR/PO created through ME51n or ME21N linking with order etc.
Regards
Terence
Hi Omkar,
Check this note
1414563 - Different assigned values in availability control/reporting
Regards
Terence