Progress analysis- Project progress based on partial confirmation of activities

former_member228466
Participant
0 Kudos

Hello friends,

One of my client using progress analysis functionalities using method (0-100), based on that he is getting the results Planned Waitage and actual waitage when the activity is fully confirmed or on 100% confirmation.

My client required the Actual should also be updated based on partial confirmation of activities.

Can you suggest how we can mapped the same or any method apart from 0- 100 as i m not getting the appropriate results from partial confirmation of activities

Note - we are not using any work center, we are assigning the no of days to activities, Planned POC and after full confirmation we are getting the actual poC.

Thanks

Yogendra Soni

Accepted Solutions (1)

Accepted Solutions (1)

former_member228466
Participant
0 Kudos

Dear Leads,

Waiting for your reply.

Thanks

Soni

Answers (0)