on 06-26-2015 7:26 AM
Hi guys,
I intend to make a cost estimate according to the valid period of production versions.
Here is the steps that I have taken.
1. Create production versions in material master data
Version 1 2015/06/01~2015/07/31 $2040
Version 2 2015/08/01~2015/09/30 $1220
2. Make a cost estimate in CK40N over the period from 2015/06/01 to 2016/03/31
I expected an estimate caculated using weighted average.
However I got the result of $2040.
Not like in CK11N, there is no field to select production version in CK40N.
I would preciate it if you could tell me what other action I should take to make a cost estimate according to the valid period of production versions.